Splitting Timecards to Other Projects
With our splitting timecards feature, you can move specific days or entire timecards from one project to another. In the event that a timecard is created under one project, but the payroll needs to be processed under another, you can move the timecard once it is completely approved. To move a timecard, go to the Timecards grid and click on the number of the timecard you would like to move. In the Grossing grid, choose the new project from the Projects drop down menu for the day(s) you would like to move, then click MOVE in the footer.. A window will open with the message that you are creating a new timecard in the project you are moving to; click CONFIRM to move.
In order to have the option to move the timecard, the employee must exist in both projects, the same position/rate must exist in both projects, and the projects must have the same work location. If you would like to utilize the timecard splitting feature, please contact application support.